Earthworks, road infrastructure, building platforms or landscaping: choosing the fill material is a decisive technical and financial step. It governs the stability, safety and durability of the finished works. Whether you are backfilling a deep trench, building a road formation or regrading natural ground, you need to know the different types of fill material and how they behave.
How do you choose between granular fill, sand, excavated soil and lightweight fill? Which geotechnical standards apply to prevent settlement and long-term structural defects? This guide sets out the main options and the selection criteria for engineers, earthworks contractors and designers.
What does fill do in a construction project?
Fill is material placed on existing ground to change its level, to fill a void (such as a former quarry or a foundation excavation) or to create a stable formation able to carry heavy loads from buildings, roads and car parks.
The choice of material determines several critical properties:
- Bearing capacity: its ability to carry loads without excessive deformation.
- Drainage behaviour: its permeability, essential for draining surface water and avoiding ponding.
- Frost susceptibility: a saturated, poorly graded fill can heave when it freezes and lift the layers above.
An unsuitable material or poor compaction can lead to serious defects – settlement, cracked ground-bearing slabs, deformed pavements – sometimes several years after handover.
Types of fill material: the main categories
Fill materials vary widely in their mechanical, physical and hydraulic properties. In the UK, earthworks materials for highway works are classified in Series 600 of the Specification for Highway Works (for example Class 1 general granular fill, Class 2 general cohesive fill and Class 6 selected granular fill); Transport Infrastructure Ireland applies an equivalent Series 600. At European level, EN 16907 (Earthworks) sets out common principles for classifying and using fill.
In practice, fill materials fall into three broad families.
Natural fill: soil, sand and gravel
Sourced from quarries or reused from site excavations (site-won material), these are the most common and usually the most economical fill materials.
- Excavated soil (cohesive soils, or granular soils with fines): often available from the site itself, it is very economical but sensitive to weather and moisture. It is well suited to landscape shaping and green areas. Under a ground slab or a pavement, its reuse depends on its moisture condition and, where necessary, on lime or cement stabilisation, to be confirmed by the geotechnical investigation.
- Sand and gravel: free-draining, with low moisture sensitivity and easy to compact, they are ideal for pipe bedding and surround, stable bedding layers and perimeter drainage of foundation walls.
Recycled and secondary fill: crushed concrete, aggregates, ash
Produced from construction and demolition waste and industrial by-products, these materials support the circular economy and are increasingly encouraged by environmental policy.
- Crushed concrete and demolition rubble: once sorted and cleaned of contaminants (steel, plastics, gypsum), these recycled aggregates offer excellent bearing capacity. They are widely used as sub-base, capping and working platforms.
- Unbound granular mixtures (such as Type 1 sub-base): blends of crushed aggregates graded at the quarry to achieve maximum density after mechanical compaction.
- Incinerator bottom ash aggregate (IBAA): can be used in road construction, subject to national regulations and environmental restrictions, particularly near watercourses and in flood-prone areas.
Lightweight fill: honeycomb blocks, EPS, expanded clay
Where the existing ground is very poor (compressible soil, soft clay, peat) or where loads on an existing structure must be kept to a minimum (podium deck, roof garden, underground car park, retaining wall, bridge abutment), lightweight fill is often the most effective solution.
Nidaplast RA honeycomb blocks are made of extruded polypropylene (60% recycled content) with a non-woven geotextile bonded to each face. They raise ground levels without adding significant weight – 35 to 45 kg/m³ depending on the grade (RA 400, RA 500 or RA 600), compared with around 2 tonnes/m³ for conventional fill – which greatly reduces settlement on compressible ground. With 95% voids, water flows freely through the cells: Nidaplast RA is a hydraulically transparent fill.
.
Nidaplast RA
Nidaplast RA lightweight embankments are extremely light and resistant. These honeycomb structures are the recommended solution for constructing landscape embankments, road embankments, or building embankments.
View product sheetFill materials at a glance
Indicative values: actual density depends on the material, its moisture content and the degree of compaction.
Fill material | Typical in-situ density | Main uses on site |
Excavated soil | 1.7 ti 200 t/m³ (compacted) | Landscape shaping, general fill in non-structural areas |
Sand and rounded gravel | 1.8 to 2.1 t/m³ (compacted) | Perimeter drainage, bedding for buried services |
Crushed concrete / recycled aggregate | 1.9 to 2.2 t/m³ (compacted) | Heavy-duty road sub-base, car park formation, foundations |
Nidaplast RA honeycomb blocks | 0.035 to 0.045 t/m³ | Fill on compressible ground, landscape fill on podium decks and roofs, bridge abutments, wetlands |
Fill under roads or around structures: which material to use?
Under heavily trafficked roads, high-bearing granular materials such as crushed aggregates are required, placed and compacted in accordance with the earthworks specification. Around buried structures (tanks, chambers, attenuation tanks), a granular material without fines is generally used, placed symmetrically in layers; the manufacturer’s installation requirements take precedence.
On compressible ground, lightweight fill limits settlement and the risk of slope instability.
Compaction and bearing capacity: key installation rules
The geotechnical performance of fill depends as much on how it is placed as on the material itself. Compaction expels air from between the particles and increases density. It must be carried out in successive layers, whose thickness depends on the material and the compaction plant (as set out in the earthworks specification), using a rammer or a heavy roller. Moisture content should stay close to the optimum determined by the Proctor test.
With lightweight blocks such as Nidaplast RA, the approach is different: the blocks are laid, not compacted; only the cover layer is compacted as specified for the project.
Standards and reference documents
The selection and placement of fill materials are covered by the following standards and guidance:
- EN 16907 (parts 1–6), Earthworks: European framework for the design, classification, construction and quality control of earthworks.
- Specification for Highway Works, Series 600 (Earthworks): classification of fill materials and compaction requirements in the UK (Series 600 of Transport Infrastructure Ireland in Ireland).
- BS 6031, Code of practice for earthworks: general rules for the design and construction of earthworks.
- Trench reinstatement: Specification for the Reinstatement of Openings in Highways (SROH) in England; Guidelines for managing openings in public roads (“Purple Book”) in Ireland.
- EN 13286-2 (Proctor compaction test) and BS 1377-9 (plate bearing test).